F&H has developed a long-term professional relationship with Prince George’s Hospital Center (PGHC) providing specialized mechanical, electrical and structural engineering design for many of the hospital’s renovation projects. For over fifteen years PGHC has relied on our engineering services. A summarized list of projects that our firm has completed for Prince George’s Hospital Center is listed below.
Emergency Department:
Design of the mechanical and electrical system for renovation of the emergency department.
Isolation Rooms:
Design of the mechanical and electrical system for conversion of twelve existing patient rooms into isolation rooms. Preparation of mechanical and electrical construction documents and performance of construction phase services for conversion of the existing patient rooms into the patient isolation rooms.
Automatic Transfer Switch (ATS) Replacement:
Electrical design for the replacement of six existing Automatic Transfer Switches serving the Hospital’s Emergency System. Preparation of electrical construction documents and construction phase services for the Replacement of the replacement of the existing Automatic Transfer Switches.
Nursery Modifications:
Design of the HVAC system for conversion of existing patient rooms into a nursery room.
Elevators:
Design of the electrical system for addition of the existing elevators to the emergency generator.
Emergency Lighting:
Design of emergency lighting system for existing operating rooms.
Ultrasound Rooms:
Design of split air conditioning units to supplement existing building HVAC system serving the ultrasound rooms.
Some of the additional projects at Prince George’s Hospital Center, for which F&H Consultants has provided MEP and structural engineering services are as follows:
Air Handling Units replacements for various areas.
Emergency Department renovations.
Renovations of Ultrasound rooms.
Renovations of the exam and clean utility rooms.
Renovation of the ninth-floor conference room.
Renovation of the first-floor.
First floor laboratory area.
Four isolation rooms in the ICU wing.
Two isolation rooms in the PACU.
One isolation room, K wing, fifth floor.
CT scan, Cath Lab and x ray room renovations.
Medical records renovations.
Sterilization/decontamination areas.
Ebola evaluation center.
Renovation of the special procedure area.
Main switchgear replacement.
Backup power for the chillers in the boiler plant.
Study of the emergency generators serving the entire hospital.
Study of the central chilled water system serving the entire hospital.
Structural study of the Helipad.
Behavioral Health Renovations Department.
“H” Wing Renovations.
MIS Department renovations.
Study of the HVAC system serving the ten operating rooms and coordination with the testing & balancing and temperature control contractor.
Pharmacy, 797 modifications.
Nursery area renovations.
Automatic Transfer Switches replacement.
Fire pump, ACF building.
ACF Building, HVAC System modifications.
Compounding room renovation.
Frozen section room renovation.
Electrical survey of the entire hospital and preparation of single line power diagram.
Survey and design of the medical gas system for various areas of the hospital and adjoining Spellman building.
Cafeteria, kitchen hood.
Kitchen, drainage piping.
Kitchen, dishwasher exhaust system.